Working in Pakistan Civil Aviation Authority at New Islamabad International Airport Project since 20th December, 2014 as an Assistant Director (Electrical). Having diverse experience of Installation, Testing & Commissioning and operation of Airfield Field Lighting System, Electrical Works of Passenger Terminal Building and External Electrification Network , 132 KV Grid Station construction and operation.
1- Supervision, coordination & verification of site activities of Package-7A (Air field lighting System)
Major Site Activities Includes: - Installation, Testing & Commissioning and Energization of Runway Center Line Lights, Runway Edge Lights, Runway TDZ Lights, Approach Light, PAPI and Stop Bar Lights, Installation of CCRs
2- Supervision, coordination & verification of site activities of Package 8-B (Electrical Power & Telecom Network)
Major Site Activities Includes: - Laying, Termination & Jointing of MV & LV Cables, Installation, Testing, Commissioning and Energization of MV & LV Switchgears, Kiosks Type Substations, Transformers and DG Sets, Erection, cables termination and testing commissioning of Street Lights Poles and Security fence lights.
3- Supervision, coordination & verification of site activities of 132kV Grid Station IIAP
Major Site Activities Includes: - Installation, Testing , commissioning and Energization of 132kV GIS Bays with dual bus bar arrangement, Power Transformer, capacitor Bank, surge arrestor, 132kV control Panels and protection panels, 11kV outgoing , Incoming and capacitor control Panels, Battery bank and battery Charger, Generator, Auxiliary Transformer and Telecom Equipment.
4- Supervision and coordination of activities of Package-8B1 (External Electrification Work of Islamabad Airport)
Major Site Activities Includes: - Laying, Termination and Jointing of MV & LV cables, Installation, Testing Commissioning and Energization of Kiosks, Transformers, Feeder Pillars, LTODS, and RMUs, Electrification of Security watch Towers and Cargo Complex , Cable termination and Installation of MV/LV Panels, Installation of DC supply system and Transformer in Cargo Substation.
5- Supervision of site activities of Package-3 (Passenger Terminal Building) Major activities include overseeing Installation, Testing and commissioning of Transformers, HT & LT Panels, DG Sets, Centralized UPS, LED Lighting Fixtures and Generators.
• Maintenance of complaints log register, preparation and submission of daily report of Federal complaint and redress Centre (FCRC) to Joint Secretary (E&D) and preparation of weekly and monthly look ahead plan.
• To prepare evaluation reports of village electrification projects.
• To prepare feasibility reports for implementation of projects related power distribution, especially installation of smart meters.
• To co-ordinate with USAID representatives regarding Technical matters related to power distribution companies.